The Channel District improvements involve the design and construction of right-of-way areas along nine street segments within the Channel District of Tampa, Florida.

The project will provide improved pedestrian access; upgrading of water, wastewater, and stormwater utilities; streetscaping (lighting and landscaping); the addition of on-street parking and sidewalks; and street furniture throughout the district.

$13.5 million has been budgeted for this project.

The overall project is expected to be complete by early 2027.

The project involves nine (9) segments divided into fifteen (15) phases as outlined below:

 

  • Phase A1 – N. 12th Street, from E. Kennedy Boulevard to E. Washington Street
  • Phase A2 – N. 11th Street, from E. Kennedy Boulevard to E. Washington Street
  • Phase B1 – Channelside Drive, from E. Kennedy Boulevard to E. Cumberland Avenue
  • Phase B2 – Intersection of E. Cumberland Avenue and Channelside Drive
  • Phase C1a – E. Twiggs Street, from N. 12th Street to Channelside Drive
  • Phase C1b – E. Twiggs Street, from N. 12th Street to N. Meridian Avenue
  • Phase C2 – E. Cumberland Avenue, from Channelside Drive to S. Meridian Avenue
  • Phase C3 – Port Tampa Bay, Terminal 3
  • Phase D1 – E. Whiting Street, from N. Meridian Avenue to N. 11th Street
  • Phase D2 – E. Whiting Street, from N. 11th Street to Channelside Drive
  • Phase DW2-1 – Intersection of E. Washington Street and N. 12th Street
  • Phase E1 – N. 12th Street, north of E. Twiggs Street
  • Phase E2 – N. 11th Street, from E. Whiting Street to E. Washington Street
  • Phase E3 – N. 12th Street, from E. Whiting Street to E. Cumberland Avenue
  • Phase WM – Meridian Avenue, north of E. Twiggs Street and N. 12th Street, from N. Raymond Avenue to the northern right-of-way of FL-618 (Selmon Expressway)

The projects phases will overlap; however, we will be sequencing the work to minimize impact to the business/residents in the Channel District.

Construction will typically take place between the hours of 7:00 a.m. and 4:00 p.m., with occasional nighttime work to occur as needed, to minimize traffic disruptions.

Construction will take place Monday through Friday, with occasional weekend work to occur on an as-needed basis to minimize traffic disruptions.

Construction activities that require temporary road closures and/or detours will be clearly marked by signage to assist motorists, pedestrians and bicyclists navigate through and around construction zones. In some cases, flagmen will be present to direct traffic. Temporary road closures and detour information will also be posted on the Alerts page.

Normal access to properties will be affected as construction progresses along the project’s phases. Property owners/tenants will be notified prior to activities impacting normal access via written notifications/flyers. Construction crews will work to minimize the duration of disruption and will ensure an alternate access route is maintained as necessary.

To avoid/minimize impacts to mail delivery and garbage/recycling pick-up, the contractor will work to coordinate with service providers concerning construction activities. Any service interruptions should be reported by calling the project hotline at 813-774-3246 or emailing [email protected].

If we are installing new water mains on a particular block, there will be a short-term service disruption.  This will last between 15-30 minutes and you will be notified weeks in advance of the interruption.

A public information meeting was conducted on July 30, 2019 at the Stageworks Theatre to inform property owners, residents, and businesses located along the project segments of project plans, schedules, and activities. Prior to the start of construction of each project phase, notification of upcoming construction activities and associated impacts will be provided to those located along the upcoming phase via written notifications/flyers, mailouts, email, and/or face-to-face. Updated project information will also be listed on the Alerts page.

You can receive updates on the City’s Channel District Improvements project by visiting the “Alerts” page. This page will be regularly updated with real time project information. You can also call the project hotline at 813-774-3246 or email the community outreach team at [email protected].

Web Accessibility

The developers of the Channel District Projects website strive to ensure that its services are accessible to people with disabilities, with the strong belief that every person has the right to live with dignity, equality, comfort and independence both in life, and on the internet.

Please consider using the accessibility menu which can be enabled by clicking the accessibility menu icon on the bottom right hand side of the screen. This can assist in viewing web page elements by altering font type, font size, color contrast, color saturation, cursor size, as well as highlighting links.

Despite our efforts to make all pages and content fully accessible, some content may not have yet been fully adapted to the strictest accessibility standards. This may be a result of not having found or identified the most appropriate technological solution. If you are unable to use any aspect of this website, PDF files, or other attachments, we can provide you with prompt assistance. Please let us know by emailing [email protected].